SAVANNA VILLAS Timeline

February 2025


  • Initial site clearing and preparation.
  • Plot marking and villa layout staking.
  • Material delivery and setup of temporary site infrastructure.

March 2025


  • Final site grading.
  • Excavation for foundation pads.
  • Kickoff of foundation works.

April-May 2025


  • Reinforcement and casting of all villa foundation slabs.
  • Pool structures completed in parallel: pool shells cast, technical rooms prepared, and septic/reservoir systems installed.

June 2025


  • First-floor columns raised.
  • Beams and partial first-level slab poured.

July 2025


  • First-floor column works completed.
  • First-level slab fully cast.
  • Second-floor column works initiated.

August 2025


  • Second-level columns and beams completed.
  • Partial casting of the second-floor slab.

September 2025


  • All second-floor columns completed.
  • Formwork and rebar preparation for rooftop slabs.
  • Initial rooftop slab pours.

October 2025


  • Rooftop terrace beams, slabs, and formwork across the complex.
  • Structural frame approx. 80% complete.

November 2025


  • All columns, beams, slabs, and rooftop structures fully completed.
  • Blockwork/wall construction underway.
  • First villa facade works started + MEP rough-ins initiated.

December 2025


In Progress...